The State Railway of Thailand (SRT) has pushed ahead with the double-tracking of its metre-gauge network to lay the groundwork for opening the rail transport market to competition starting in 2028. On the 144 km Nakhon Ratchasima – Kaeng Khoi line, construction progress stood at 95% in May 2026, with completion scheduled for 2027. The project, which has been underway since 2018, initially comprised seven contract packages covering 993 km and valued at around EUR 3.4 billion (USD 4 billion). Several sections are already complete, including Nakhon Ratchasima – Khon Kaen and Nakhon Pathom – Kaeng Khoi. A key focus is on connections to Laos. The new 355 km Ban Phai – Nakhon Phanom line was about one-third complete as of June 2026, the new completion date is November 2029. The 323.1 km Den Chai – Chiang Rai – Chiang Khong line reached 57% construction progress in May 2026 and is slated for completion in 2028. In December 2024, SRT awarded a construction contract worth EUR 732 million for the 167 km Khon Kaen – Nong Khai expansion. Concurrently, SRT awarded contracts for signaling technology including the European Train Control System (ETCS) Level 1, interlocking systems and transport control systems to companies such as LS Electric, Hitachi Rail, Siemens Mobility, and Progress Rail. Under the Railway Act that came into force on 27th March 2026, SRT retains its role as infrastructure operator but is required to open track access to private providers starting in 2028.