The Japanese Shizuoka Prefecture and JR Central have reached an agreement on environmental protection measures to allow the resumption of construction on the Chuo magnetic levitation (maglev) line between Tokyo and Nagoya. The earliest date for the launch of the 286 km first section is now set for 2036, rather than 2027. Construction had been suspended since 2017 after the then-governor of the Shizuoka Prefecture raised objections regarding tunnelling work beneath the Oi River. Concerns centred on potential impacts on water flow, the ecological balance and the regional water supply. Planning for the commercial line running from Shinagawa via Nagoya to Osaka began in the 2000s, with construction starting in 2014. Costs for the initial section to Nagoya rose from an original EUR 29.8 billion (JPY 5.5 trillion) to EUR 59.6 billion. JR Central secured government investments and loans totalling around EUR 16.2 billion for the project. Meanwhile, testing of the SCMaglev technology continued. In 2012 and 2013, Nippon Sharyo and Mitsubishi built two seven-car pre-production trains of the L0 series, designed for speeds of 505 km/h. In 2015, a train reached a speed of 603 km/h on the Yamanashi test track. Hitachi Rail subsequently took over further development and manufacturing.